Leipzig municipial utilities

Earthworks Leipzig municipal utilities
Construction project: earthworks
Client: Stadtwerke Leipzig
Place of execution: Leipzig
Construction time: 4 months
Scope of services:
-
Earthworks, excavation of approx. 5000 m³ of soil
-
Demolition and disposal of approx. 3000 m³ of concrete foundations
-
Backfilling of 1000 m³ coarse aggregate and 1000 m³ mineral mixture
-
Water retention using pump sumps
Technical and device-specific features:
-
2 excavators 40 t
-
Wheel loader 10 t
![]() | ![]() | ![]() | ![]() | ![]() |
---|

ILSENBURG

Excavation work Ilsenburg
Construction project: New finishing line II, Lot: Earthworks
Client: Ilsenburger Grobblech GmbH, ARGE BeMo/Heitkamp
Place of execution: Site of Ilsenburger Grobblech GmbH, Ilsenburg
Construction time: approx. 2 years (Sept 2017 - Aug 2019)
Scope of services:
-
Demolition and disposal of existing buildings approx. 20,000 m³ u. R.
-
Soil improvement of approx. 35,000 m³
-
Excavation pit with a volume of approx. 150,000 m³
-
Backfilling of approx. 20,000 m³ including installation and compaction
Technical and device-specific features:
-
4 crawler excavators 30-50 tons with protective ventilation (work in contaminated areas)
-
Soil improvement by adding binding agent (lime-cement mixture)
![]() | ![]() | ![]() | ![]() | ![]() |
---|