Krumpa
Construction project: ILP Geiseltalsee Krumpa, formerly ADDINOL Mineralöl GmbH iGV,
MK 8.5.3 Renovation of ATL I and II
Client: MDSE Central German Renovation and Waste Disposal Company mbH
Place of execution: Krumpa
Construction time: 9 months (May 17, 2016 - January 31, 2016)
Scope of services:
-
Demolition of old foundations 3000 m³
-
Exchange of contaminated soil (MKW, BTEX, PAH) 24,000 m³
-
Microbiological on-site treatment of 17,200 m³ of soil
-
Terrain profiling 7000 m²
-
Disposal of non-treatable contaminated soil
Technical and device-specific features:
-
Earth-moving machines (crawler excavators) with protective ventilation
-
terraclean® process (on-site process)
-
Working in contaminated areas according to DGUV Rule 101-004 formerly BGR 128
![]() | ![]() | ![]() |
---|