CONTAMINATED SITE REMEDIATION

Krumpa

Construction project: ILP Geiseltalsee Krumpa, formerly ADDINOL Mineralöl GmbH iGV,

MK 8.5.3 Renovation of ATL I and II

Client: MDSE Central German Renovation and Waste Disposal Company mbH

Place of execution: Krumpa

Construction time: 9 months (May 17, 2016 - January 31, 2016)

 

Scope of services:

  • Demolition of old foundations 3000 m³

  • Exchange of contaminated soil (MKW, BTEX, PAH) 24,000 m³

  • Microbiological on-site treatment of 17,200 m³ of soil

  • Terrain profiling 7000 m²

  • Disposal of non-treatable contaminated soil

 

Technical and device-specific features:

  • Earth-moving machines (crawler excavators) with protective ventilation

  • terraclean® process (on-site process)

  • Working in contaminated areas according to DGUV Rule 101-004 formerly BGR 128

 